Civil Engineering MCQs: 3,057 practice questions with answer choices and available explanations. Page 159 of 204.

Civil Engineering MCQs by topic

Now you can submit the latest Civil Engineering MCQs MCQs from your test! SUBMIT HERE

Civil Engineering MCQs

Showing page 159 of 204 · 3,057 total solved questions available.

Study Topic
Start Quiz Mode to Practice Like the Real Exam!
A.Circular septic tanks
B.Rectangular septic tanks
C.Circular Imhoff double storey tanks without bottom hoppers
D.Circular Imhoff double tanks with bottom hoppers
Explanation: The correct answer is Circular Imhoff double storey tanks without bottom hoppers.

Submitted by: Academy of Pakistan

Share
A.The earth work in trenches or borrow pits in irregular ground is measured by taking the difference in levels before and after completion of work
B.The earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men
C.All the above
D.The earth work in trenches or borrow pits, where neither a nor b is feasible, are measured from the fillings after deduction of voids
Explanation: The correct answer is All the above.

Submitted by: Academy of Pakistan

Share
A.Critical activity is the one for which free float is zero
B.A critical path always terminates at the last event
C.Critical activities control the project duration
D.A critical path always begins at the very first event
Explanation: The correct answer is Critical activity is the one for which free float is zero.

Submitted by: Academy of Pakistan