A.identify the activities, which can be delayed without affecting the total float of succeeding activity
B.establish priorities
C.identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
D.identify the activities which can be delayed without affecting the total float of preceding activity
Explanation: The correct answer is identify the activities, which can be delayed without affecting the total float of succeeding activity.