3729Chemical EngineeringMedium
________ method for profitability evaluation of a project does not account for investment cost due to land?
APay out period
BDiscounted cash flow
CRate of return on investment
DNet present worth
Correct answer
A. Pay out period
Explanation
The correct answer is Pay out period.