1248Civil EngineeringMedium
Pick up the item of work not included in the plinth area estimate________?
AWall thickness
BW.C. area
CCourtyard area
DRoom area
Correct answer
C. Courtyard area
Explanation
The correct answer is Courtyard area.
Correct answer
C. Courtyard area
Explanation
The correct answer is Courtyard area.
The continuity equation pi V,A,= p2V2A2 is based on the following assumption regarding flow of fluid________?
Antisyphonage pipe is fitted________?
If a concrete column 200 × 200 mm in cross-section is reinforced with four steel bars of 1200 mm2 total cross-sectional area. Calculate the safe load for the column if permissible stress in concrete is 5 N/mm2 and Es is 15 Ec________?
If a beam fails in bond, then its bond strength can be increased most economi-cally by________?
The side slope of embankments for a railway track is generally taken as________?
The amount of reinforcement for main bars in a slab, is based upon________?