1289Civil EngineeringMedium
Total float for any activity is defined as the difference between________?
Aits latest finish time and earliest start time for its successor activity
Bits latest start time and earliest start time
Cits earliest finish time and earliest start time for its successor activity
Dits latest start time and earliest finish time
Correct answer
B. its latest start time and earliest start time
Explanation
The correct answer is its latest start time and earliest start time.