The reduction in project time normally results in________?
Adecreasing the direct cost and increasing indirect cost
Bincreasing the direct cost and indirect cost both
Cincreasing the direct cost and decreasing the indirect cost
Ddecreasing the direct cost and indirect cost both
Correct answer
C. increasing the direct cost and decreasing the indirect cost
Explanation
The correct answer is increasing the direct cost and decreasing the indirect cost.