If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is________?
A6 days
B4 days
C16 days
D10 days
Correct answer
C. 16 days
Explanation
The correct answer is 16 days.