1611Civil EngineeringMedium
As compared to crest of the normal portion of the weir, the crest of the under sluice portion of weir is kept at________?
Ahigher level
Bsame level
Clower level
Dany of the above depending on the design
Correct answer
C. lower level
Explanation
The correct answer is lower level.