1739Civil EngineeringMedium
Economic saving of time results by crashing________?
Acostliest critical activity
Bcheapest critical activity
Ccostliest non-critical activity
Dcheapest non-critical activity
Correct answer
B. cheapest critical activity
Explanation
The correct answer is cheapest critical activity.