1795Civil EngineeringMedium
If the R.L’s of canal bed level and high flood level of drainage are 212.0 m and 210.0 m respectively, then cross drainage work will be________?
Aaqueduct
Bsyphon aqueduct
Csuperpassage
Dsyphon
Correct answer
D. syphon
Explanation
The correct answer is syphon.