1806Civil EngineeringMedium
In PERT analysis, the time estimates of activities and probability of their occurrence follow________?
APoisson’s distribution curve
Bnormal distribution curve
CBeta – distribution curve
Dnone of the above
Correct answer
C. Beta – distribution curve
Explanation
The correct answer is Beta – distribution curve.