1937Civil EngineeringMedium
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then________?
Anone of the above
Bexpected time of activity A is greater than the expected time of activity B
Cexpected time of both activities A and B are same
Dexpected time of activity B is greater than the expected time of activity A
Correct answer
C. expected time of both activities A and B are same
Explanation
The correct answer is expected time of both activities A and B are same.