A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand for the generators is 35 units. The line operates for 7 hours per day, 5 days per week. What is the maximum production time per unit in hours required of the line to meet the demand?
Correct answer
D. 1.0 hour per unit
Explanation
The correct answer is 1.0 hour per unit.