2143Civil EngineeringMedium
If the peak discharge of a storm water drain (S.W. Drain) is expected to exceed 150 cumecs, the free board to be provided, is________?
A100 cm
B80 cm
C90 cm
D50 cm
Correct answer
A. 100 cm
Explanation
The correct answer is 100 cm.