2376Civil EngineeringMedium
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________?
Alongest duration
Bhighest cost slope
Cshortest duration
Dleast cost slope
Correct answer
D. least cost slope
Explanation
The correct answer is least cost slope.