Removal of props under________?
Aslabs spanning upto 4.5 m is 7 days
BAll the above
Cslabs spanning upto 4.5 m is 14 days
Dbeams spanning upto 6 m is 14 days
Correct answer
B. All the above
Explanation
The correct answer is All the above.