2861Civil EngineeringMedium
Latest start of an activity is always________?
Aless than latest event time of preceding node
Bless than or equal to latest event time of preceding node
Cequal to latest event time of preceding node
Dgreater than or equal to latest event time of preceding node
Correct answer
D. greater than or equal to latest event time of preceding node
Explanation
The correct answer is greater than or equal to latest event time of preceding node.