In time-cost optimization of a project, crashing is done________?
Aon all the activities lying on the critical path
Bonly on activities lying on the orginal critical path and having flatter cost slopes
Con original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Don all the activities
Correct answer
C. on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Explanation
The correct answer is on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope.