Pick up the correct statement from the following?
AThe earth work in trenches or borrow pits in irregular ground is measured by taking the difference in levels before and after completion of work
BThe earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men
CAll the above
DThe earth work in trenches or borrow pits, where neither a nor b is feasible, are measured from the fillings after deduction of voids
Correct answer
C. All the above
Explanation
The correct answer is All the above.