Select the incorrect statement?
ACritical activity is the one for which free float is zero
BA critical path always terminates at the last event
CCritical activities control the project duration
DA critical path always begins at the very first event
Correct answer
A. Critical activity is the one for which free float is zero
Explanation
The correct answer is Critical activity is the one for which free float is zero.