43Civil EngineeringMediumIn the critical path method of construction planning, Free Float can be________?A2 and 3 are correctB1 and 2 are correctC1 and 4 are correct Correct answerA. 2 and 3 are correct ExplanationThe correct answer is 2 and 3 are correct.