571Civil EngineeringMedium
Select the incorrect statement?
AThe progress of work in low level method of mound construction is very slow.
BIn low level method of mound construction, the area of working is limited.
CBarge method of mound construction is economical.
DIn staging method of mound cons-truction, the work is not interrupted even during stormy weather
Correct answer
C. Barge method of mound construction is economical.
Explanation
The correct answer is Barge method of mound construction is economical..