751Civil EngineeringMedium
What characteristic best describes the cost baseline?
ATotal budget for the project including the contingency budget
BTotal budget for the project including the contingency budget and the management reserve
CTotal budget for the project
DTime phased budget for the project
Correct answer
D. Time phased budget for the project
Explanation
The correct answer is Time phased budget for the project.