884Civil EngineeringMedium
Select the correct statement?
AActivity arrows in a CPM network are drawn to scale
BThe tail of an arrow represents the finish of an activity
Cnone of the above
DArrow bead represents the start of an activity
Correct answer
C. none of the above
Explanation
The correct answer is none of the above.