The situation in which one project is accepted while rejecting an other project in comparison is classified as __________?
Amutual consent
Bmutual project
Cpresent value consent
Dmutually exclusive
Correct answer
D. mutually exclusive
Explanation
mutually exclusive is the correct answer. Review the question and compare it with the other choices to remember this fact for future exams.