Projects which are mutually exclusive but different on scale of production or time of completion then the___________?
AInternal return method
BExternal return method
CNet future value method
DNet present value of method
Correct answer
D. Net present value of method
Explanation
Net present value of method is the correct answer. Review the question and compare it with the other choices to remember this fact for future exams.