Pick up the incorrect statement from the following?
Athe tail of the arrow indicates the start of the activity
Ban activity of the project is denoted by an arrow on the net work
Cthe arrows are drawn (to scale from) left to right
Deach activity consumes a given time
Ethe head of the arrow indicates the end of,the activity!
Correct answer
C. the arrows are drawn (to scale from) left to right
Explanation
The correct answer is the arrows are drawn (to scale from) left to right.