1014Mechanical EngineeringMedium
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to________?
Anone of the above
BTL-EFT
Clatest finish time – earliest finish time (EFT)
Dlatest start time – earliest start time
Eall of the above
Correct answer
E. all of the above
Explanation
The correct answer is all of the above.