Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it________?
Aconsumes both resources and time
Bconsumes time, but no resources
Cconsumes neither time nor resources
Dis a dangling event
Econsumes resources but no time
Correct answer
C. consumes neither time nor resources
Explanation
The correct answer is consumes neither time nor resources.