1076Mechanical EngineeringMedium
The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is Known as________?
Ainterfering float
Bnone of the above
Cfree float
Dduration
Etotal float
Correct answer
C. free float
Explanation
The correct answer is free float.