1392Mechanical EngineeringMedium
Pick up the correct step used for scheduling a project by C.P.M.________?
Asequence of various activities is made according to their importance
Brequired time for each activity is established
Call of the above
Dnetwork is drawn by connecting the activities and the events
Ea project is divided into various activities
Correct answer
C. all of the above
Explanation
The correct answer is all of the above.