1456Mechanical EngineeringMedium
The safety valve on boiler drum compared to safety valve on super heater is set at ________?
Ahigher value
Blower/higher depending on steam flow
Clower value
Dsame value
Eunpredicatble
Correct answer
A. higher value
Explanation
The correct answer is higher value.