1639Mechanical EngineeringMedium
Descripancies of bar chart techniques are________?
Aall of the above
Bconsequential effects of lack in one activity on the finish date
Ceffective monitoring/controlling can’t be done
Dconsequential effects of lack in one activity on omer
Efree time available for an activity can’t be predicted
Correct answer
A. all of the above
Explanation
The correct answer is all of the above.