The critical path of a network represents________?
Anone of the above
Bthe minimum time required for completion of project
Cmaximum cost required for completion of project
Dminimum cost required for completion of project
Ethe maximum time required for completion of project
Correct answer
B. the minimum time required for completion of project
Explanation
The correct answer is the minimum time required for completion of project.