1751Mechanical EngineeringMedium
Pessimistic time is________?
Athe minimum time in which an activity can possibly be accomplished
Bthe maximum time which an activity might require
Cthe most probable time considering all conditions
Dthe average time required for a job
Ethe earliest finish
Correct answer
B. the maximum time which an activity might require
Explanation
The correct answer is the maximum time which an activity might require.