Pick up the correct statement from the following?
Aif the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
Bthe float may be positive, zero or negative
Cif the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed
Dif the float of an activity is negative, delay in its performance is bound to delay the completion of project
Eall of the above
Correct answer
E. all of the above
Explanation
The correct answer is all of the above.