1917Mechanical EngineeringMedium
Critical Path Net Work helps an engineer________?
Ato concentrate his attention on critical activities
Bto divert the resources from non-critical advanced activities to critical activities
Call of the above
Dnone of the above
Eto be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
Correct answer
C. all of the above
Explanation
The correct answer is all of the above.