1922Mechanical EngineeringMedium
An optimum project schedule implies________?
Aoptimum utilization of men, machines and materials
Blowest possible cost and shortest possible time for project
Crealistic execution time, minimum cost and maximum profits
Dto produce best results under given constraints
Etimely execution of project
Correct answer
B. lowest possible cost and shortest possible time for project
Explanation
The correct answer is lowest possible cost and shortest possible time for project.