1965Mechanical EngineeringMedium
Scheduling gives information about________?
Athat how idle time can be minimized
Bwhen work should complete
Cwhen work should start and how much work should be completed during a certain period
Dnone of the above
Eproper utilisation of machines
Correct answer
C. when work should start and how much work should be completed during a certain period
Explanation
The correct answer is when work should start and how much work should be completed during a certain period.