In a PERT chart________?
Ano activity is numbered
Bonly selected activities are numbered
Call activities should be numbered
Donly important activities should be numbered
Eonly critical activities are numbered
Correct answer
C. all activities should be numbered
Explanation
The correct answer is all activities should be numbered.