Slack represents the difference between the________?
Anormal allowable time and the latest expected time
Blatest allowable time and the earliest expected time
Cproject initiation tune and actual starting time
Dlatest allowable time and the normal expected time
Eproposed allowable time and the earliest expected time
Correct answer
B. latest allowable time and the earliest expected time
Explanation
The correct answer is latest allowable time and the earliest expected time.