Activity s,lack or float of any event on a PERT/CPM chart is represented by________?
Alatest start time of succeeding event -earliest finish time of preceding event activity time
Blatest start time of the event – earliest start time of the event
Canyone of the above
Dnone of the above
Elatest finish time of event – earliest finish time of the event
Correct answer
C. anyone of the above
Explanation
The correct answer is anyone of the above.