632Mechanical EngineeringMedium
PERT is________?
Aan analytic tool in concept
Blimit up of event oriented diagrams
Call of the above
Dbased on three time estimates for activities linking up two events
Eused for research and development projects
Correct answer
C. all of the above
Explanation
The correct answer is all of the above.