Criticalpath on PERT/CPM chart is obtained by joining the events having________?
Ajudgement and experience
Bno slack
Cminimum slack
Daverage slack
Emaximum slack
Correct answer
C. minimum slack
Explanation
The correct answer is minimum slack.