Mohamand Dam which is being constructed on swat river will completed at the cost of Rs.________billion by 2024?
Correct answer
D. Rs. 183 billion
Explanation
Rs. 183 billion is the correct answer. Review the question and compare it with the other choices to remember this fact for future exams.