The power generation capacity of the Diamer Bhasha project will be_________?
A3500MW
B4500MW
C2500MW
D3000MW
Correct answer
B. 4500MW
Explanation
4500MW is the correct answer. Review the question and compare it with the other choices to remember this fact for future exams.