1012Software EngineeringMedium
Which of the following process is concerned with analyzing the costs and benefits of proposed changes?
ARelease management
BChange management
CVersion management
DSystem building
Correct answer
B. Change management
Explanation
Explanation: It involves approving those changes that are worthwhile, and tracking which components in the system have been changed.