1584Software EngineeringMedium
The Capability Maturity Model (CMM) is a continuous model?
AFalse
BTrue
Correct answer
A. False
Explanation
Explanation: The CMM is discrete rather than continuous.
Correct answer
A. False
Explanation
Explanation: The CMM is discrete rather than continuous.