1736Software EngineeringMedium
Which of the following is not an option to achieve reliable cost and effort estimate?
ABase estimates on similar projects that have already been completed
BUse relatively simple decomposition techniques to generate project cost and effort estimates
CUse one or more empirical models for software cost and effort estimation
DThe ability to translate the size estimate into human effort, calendar time, and dollars
Correct answer
D. The ability to translate the size estimate into human effort, calendar time, and dollars
Explanation
The correct answer is The ability to translate the size estimate into human effort, calendar time, and dollars.