As per an IBM report, “31%of the project get cancelled before they are completed, 53% overrun their cost estimates by an average of 189% and for every 100 projects, there are 94 restarts”.What is the reason for these statistics?
AAll of the mentioned
BManagement issues in the company
CLack of software ethics and understanding
DLack of adequate training in software engineering
Correct answer
D. Lack of adequate training in software engineering
Explanation
Explanation: Option b & c are a part of Software Engineering as a subject,hence option a covers them both.